Background
The client is a customer for the reconstruction of several production halls in order to expand production.
Under the construction contract, the general contractor was hired, who significantly violated the work deadline and failed to commission the facility in accordance with the terms of the contract.
What did we help with?
In preparation for the trial, REVERA prepared
Progress of the proceedings
After the court accepted the claim for liquidated damages, the defendant filed a counterclaim to declare the construction contract null and void.
Based on the results of the analysis of the counterclaims, a draft objection was prepared.
The interests of the client were represented in court by a lawyer from the Minsk Regional Bar Association, with whom REVERA lawyers worked closely, jointly adjusting the case strategy.
The court ruling
The ruling of the court hearing the economic case was the following:
The decision was appealed against by the defendant. The appeal was rejected.