The client is a customer for reconstruction of a production workshop (plant);
The Customer and the General Contractor entered into a turnkey general construction contract for the reconstruction of the plant at a cost of over RUB 20 million;
The Client provided the General Contractor with an advance payment of RUB 3.7 million;
The general contractor has contracted the works for the amount of RUB 0.8 million. After six months, the construction actually stopped, the deadlines were significantly violated;
The customer refused to fulfil the contract and filed a lawsuit for recovery of unearned advances in the amount of RUB 2.9 million.
In preparation for the trial, REVERA has prepared:
| Claimant | Defendant |
|
|
The court verified compliance with the essential conditions for the conclusion of the contract and recognised it as concluded;
The Court assessed the Employer’s unilateral refusal and found it to be justified;
The court requested:
The defendant claimed that the work had been carried out by its subcontractors without providing any documents;
The court appointed a construction-technical expertise.
The client’s interests in court were represented by a lawyer of the Minsk Regional Bar Association, with whom REVERA lawyers closely co-operated, jointly adjusting the case strategy.
The General Contractor did not provide the expert with the performance documentation and certificates of completed works;
The Respondent was unable to specify the locations of the works which had previously allegedly not been accepted by the Employer;
According to the expert’s explanations, it is not possible to establish the work performed by the Respondent without providing executive documentation;
In the research part, the expert indicated what types of work were generally performed at the site
The Respondent’s arguments that the Claimant must prove by whom the work was performed are contrary to the law, since the procedure for presenting the work, confirming its scope and quality was not observed by the Respondent;
The risks of the Respondent’s failure to provide evidence in the case file are borne by the Respondent;
The Respondent did not prove acceptance of any works from the subcontractors, did not submit any documents in terms of the existence of claims to the subcontractors, sending them certificates of completed works, executive documentation, etc., therefore, the Respondent did not accept the said works from the subcontractors;
The existence of the works claimed by the Respondent has not been confirmed by examination;
The bill of lading for materials cannot be a proof of work performance in the absence of the materials write-off list and the absence of these costs in the accounting data of the Respondent;
To satisfy the Client’s claims in part (minus the cost of the transformer substation confirmed by the expert). To recover RUB 2.28 million from the defendant.
The decision was appealed by the Respondent. The appeal was dismissed.
Dear journalists, the use of materials from the REVERA website in publications is only possible after our written permission.
For materials coordination, please contact by e-mail: i.antonova@revera.legal or Telegram: https://t.me/PR_revera